Land and Real Property




Status: Ongoing

 

Full Activity Title: Cadastral works and registration of ownership rights to land parcels and buildings within the rehabilitation/construction corridor along Marabda-Akhalkhalaki-Karsi railway

 

Location: Kvemo Kartli and Samtskhe-Javakheti  regions, Georgia

 

Activity Dates: October, 2007 - July, 2012

 

Source of Funding: Marabda-Kartsakhi Railway LTD

 



Project Abstract:

In February, 2007, Georgia, Turkey and Azerbaijan  signed trilateral agreement  to carry out Baku-Akhalkalakhi-Karsi railway project. The new route will connect  Chine, Central Asia, Transcaucasus and European countries. 15 million  tons of cargo can be transited each year through the new railway after the completion of the project.

 

The project envisages building of 98 km railway line between Akhalkhalaki and Karsi. 29 km of this segment is on the Georgian territories and 70 km on the Turkish side. Rehabilitation of the old obsolete Tbilisi-Akhalkalaki segment of the existing railway is also planned on the territory of Georgia.

 

Before construction and rehabilitation works, registration of ownership rights to the land parcels and buildings existing along the construction /rehabilitation corridor is essential. Marabda-Kartsakhi LTD, operator company on the Georgian territory of railway project, contracted APLR to carry out title registration.

 

Within the scope of the project APLR carries out cadastral works on the land parcels and buildings along 150 km line from Tbilisi to Akhalkhalaki and 29 km line from Akhlalkalaki to Karsi, identifies privately owned parcels and their owners, ensures map preparation and title registration at public registry;  as well as defines the price for the land parcels to be included in chartered capital of operator company. As a result the client gets extract from public registry on each registered unit, as well as digital and printed maps, database for registered objects  (including information on the area, identification code and address)  and data on the owners of privately owned parcels within construction/rehabilitation corridor.

 

The works carried out under the project ensures fast implementation of construction and rehabilitation works in Georgia and  supports  successful completion of Baku-Akhalkhalaki-Karsi railway project.